Thursday, October 2, 2008

On-Site Meeting with Tree Company

Today we met with the folks from Goods Tree Care on the lot itself. This is one tricky (and tree-filled) lot! It was a first-look for many at the lot. We decided it was best to have the engineer stake the centerline of the driveway - and the approximate location of the house. This way, we can determine the extent of tree removal.

We also have a tentative scheduled date for the Superior Walls - October 29th - though I'm not sure we'll be ready for them yet.... We're still waiting on the building permits. In the meantime, we want to get the lot ready for the house.

Also, Murus gave me an estimated 7 weeks lead time for the SIPs. Hopefully, we can move that timeline up....